(08-21-2023, 01:47 PM)Gzbaggy Wrote: They might have been identified for commercial development but little if any has taken place. The site opposite Lichfield City train station has been derelict for at least five years. There has been little development along the end of Eastern Avenue between the Doctor Johnson and the Friary School for years. If you are saying that you cannot build houses on them because of commercial development then is it not unreasonable to ask when that development will take place?
Another point about Lichfield is that there are few jobs based there, the biggest employer is probably Tescos!
The site I worked on at Liberty Park took several years to obtain a planning consent let alone the enabling works to the West Coast Main Line and the bridge across it, electrical network reinforcement and drainage works below the A38.
Most of the commercial developments I worked on like Birch Coppice, Hams Hall, Keresley, Bermuda, Stonebridge Cross measure funding, planning, infrastructure, servicing and development over a decade or two rather than just a few years. It's a very simplistic attitude to say that "little" is taking place when I had armies of planners, engineers and services consultants working on sites that merely had a planning allocation (not a planning consent) for years.
The second phase of a 300-acre site I brought forward in Droitwich is about to come on stream 13 years after I left the industry - that's a good indication of how long things take.